Hombre Muerto West (HMW) Phase 1 Construction Update - 92% Complete
Facebook Twitter WhatsApp SMS Email Highlights: Phase 1 construction now approximately 92% complete Nanofiltration plant assembly progressing to plan Construction expected to complete in the short term, transitioning to testing and commissioning Nanofiltration plant commissioning ... ACCESS Newswire Facebook Twitter WhatsApp SMS Email Print Copy article link Save Highlights:Phase 1 construction now approximately 92% completeNanofiltration plant assembly progressing to planConstruction expected to complete in the short term, transitioning to testing and commissioningNanofiltration plant commissioning with raw brine expected to follow successful testingSignificant brine inventory ready for processingFirst lithium chloride concentrate in H1 2026, first shipment H2 2026PERTH, AU / ACCESS Newswire / March 1, 2026 / Galan LithiumLimited (ASX:GLN) (Galan or the Company) is pleased to provide an update on construction progress at its 100% owned Hombre Muerto West (HMW) Project in Catamarca Province, Argentina.Figure 1. Nanofiltration Plant at HMWConstruction Progress UpdateAssembly of the nanofiltration plant, a critical component of the Phase 1 processing flowsheet, is progressing on schedule following its recent delivery to site. With more than 25 personnel currently mobilised at HMW, structural, mechanical and electrical installation activities are advancing rapidly. The plant is being assembled on an accelerated timeline following fabrication and pre-installation testing in Sy...