M&E delay pushes Hinkley C first reactor start up back a year |  Construction Enquirer News

M&E delay pushes Hinkley C first reactor start up back a year | Construction Enquirer News

Construction Enquirer 5 min read Article

Summary

EDF's Hinkley C project faces a delay, pushing the first reactor startup to 2030, with costs rising to £48bn due to lower productivity in the electromechanical installation programme.

Why It Matters

This delay highlights ongoing challenges in large-scale infrastructure projects, particularly in the nuclear sector. The rising costs and extended timelines can impact energy policy, investment decisions, and public perception of nuclear energy's viability as a sustainable option.

Key Takeaways

  • Hinkley C's first reactor startup is delayed to 2030, a year later than previously estimated.
  • Construction costs have surged to £48bn, reflecting significant inflation and project challenges.
  • Despite progress in civil works, the electromechanical installation remains behind schedule.
  • Lessons learned from Hinkley C are being applied to the Sizewell C project, which aims to reduce costs.
  • The project’s delays may influence future nuclear energy investments and policy discussions.

EDF has confirmed lower than expected productivity on the vast electromechanical installation programme means Unit 1 is now scheduled to start up in 2030. That is a year later than the previous best-case 2029 target, itself already two years behind the earlier 2027 revised timetable and five years adrift of the original 2025 online date set when the project was approved in 2016. The latest estimate pegs construction at £35bn in 2015 prices – equivalent to £48bn today. In annual results, EDF said civil works at Unit 1 had reached 94% by concrete volume by the end of last year, the 24 primary loop welds for the reactor were finished in January and major safety injection pumps are now installed. Unit 2’s dome has been lifted into place and the reactor pressure vessel delivered. But the MEH programme remains behind schedule despite improved installation rates in the second half of 2025. EDF said recent momentum provides “a reasonable foundation” to deliver the revised timetable. EDF also revealed the Hinkley Point project had received £1.6bn payment from Sizewell C in return for expertise it supplied to the replica Suffolk nuclear power station project. Sizewell C is currently projected to cost £38bn at 2024 prices, based on achieving major savings from lessons learned during Hinkley’s construction.

Related Articles

Safety

Boral siding blade longevity

We do a lot of boral siding and have to sharpen our blades constantly to maintain precise, clean miter joints. I was debating on trying t...

Reddit - Construction · 1 min ·
Project Management

What is the industry perception of these firms?

Arcadis, MIGSO-PCUBED, Ramboll, Arup and UK Atomic Energy Authority. I am aiming for a project management degree apprenticeship with thes...

Reddit - Construction · 1 min ·
Project Management

What route is better?

Is it better to get a bs in electrical engineering and then a ms in construction management Or a bs in construction management and then a...

Reddit - Construction · 1 min ·
Safety

what changed your lead quality more than ad spend?

We tested a simple intake change: required budget range + urgency + project photos before calls. No ad changes. Lead count dipped a bit, ...

Reddit - Construction · 1 min ·
More in Project Management: This Week Guide Trending

No comments

No comments yet. Be the first to comment!

Stay updated with Construction News

Get the latest news, tools, and insights delivered to your inbox.

Daily or weekly digest • Unsubscribe anytime